Monday, 31 October 2011

Boxing Day

 Waste pipes in and sand spread out across the site. The boxing (formwork) is 300 mm high because we are building a waffle pod slab. The slab will be poured in one continuos pour at the two different levels incorporating a 600mm step.
 Boxing partly in place
 The 600mm break in level is lifted into place.
Strip footings poured, boxing finished and sand raked out.

No comments:

Post a Comment