Tuesday 25 June 2013

En suites

The ensuites are ready to go with plumbing fixtures in place, tiling and lights as well as glass screens and tap ware.





Hand basin, granite floors and tiles


Glass shower screens, shower fittings

Tuesday 11 June 2013

Interiors, doors and plaster.

The carpenters have hung the interior doors, and fitted locks etc, plastering is completed.


Doors in place



 last light down the breezeway


Plaster work in office


Fire wall in mudroom

Kitchen basics

In keeping with our recycle, reuse, ethos, we were able to source an excellent commercial stove, fitted for LPG on Ebay. Installed and ready to be commissioned, the stove should be a source of many a long table meal.

The Waldorf Range stands by ready to to start cooking with gas.


Commercial sink in place

Monday 3 June 2013

Painters final touches outside

The painters enjoyed a brief stretch of fine weather to complete the exterior painting.

All painted and polished.