Thanks to some dedicated welding from Mick and Kevin, these worn horseshoes have found the light at the end of the road. Well nearly, just got to finish the connection.
This Blog is intended to describe and track the development of the Spring Spur Riders Lounge and Accommodation Facility at the Bogong Horseback Adventures home property - Spring Spur. The development and the new products and services that will result is an exciting stage in the evolution in Bogong Horseback Adventures, and the future for the Baird family.
Monday, 15 July 2013
Tuesday, 25 June 2013
En suites
The ensuites are ready to go with plumbing fixtures in place, tiling and lights as well as glass screens and tap ware.
Hand basin, granite floors and tiles
Glass shower screens, shower fittings
Tuesday, 11 June 2013
Interiors, doors and plaster.
The carpenters have hung the interior doors, and fitted locks etc, plastering is completed.
Doors in place
last light down the breezeway
Plaster work in office
Fire wall in mudroom
Kitchen basics
In keeping with our recycle, reuse, ethos, we were able to source an excellent commercial stove, fitted for LPG on Ebay. Installed and ready to be commissioned, the stove should be a source of many a long table meal.
The Waldorf Range stands by ready to to start cooking with gas.
Commercial sink in place
Monday, 3 June 2013
Painters final touches outside
The painters enjoyed a brief stretch of fine weather to complete the exterior painting.
All painted and polished.
Friday, 17 May 2013
Finished the granite floor
Despite being heavy work, bricklayer Bernie completed the granite floors covering over 200m2 of floor. Bernie's attention to detail shows in the layout of the stone.
Granite set in place and grouted
Monday, 13 May 2013
Electrical fittings
Electrical contractor Richard has fitted the Hi Bay lights to the lounge area
One of 3 HiBays over the lounge area